Installation and Testing Sprinkler System - Method Statement

Download the Method Statement for Installation and Testing Sprinkler System👈



The Fire Sprinkler System is an Active Fire Protection method used in industries, offices, buildings, and warehouses to effectively protect against fire.

The fire sprinkler system consists of various components integrated so well that upon activation, they work together. The system basically consists of the fire sprinkler heads, piping, and most importantly, 3 pumps. The pumps are of 3 types;

  1. Jockey Pump - This pump is designed to maintain the water pressure within the piping and sprinkler heads, in case of leaking or water pressure drops. It is connected to the power supply and starts automatically whenever there is a pressure drop. It prevents the other pumps (electrical and diesel) from activation.
  2. Electrical Pump - This is the first primary pump connected to the power supply and starts working when the sprinkler system activates.
  3. Diesel Pump - This is the secondary pump or backup pump to be used in case the electrical pump is unable to get activated. Moreover, in case there is a fire ignition due to electricity and the electrical supply is shut down, then the diesel pump will be used to supply water to the sprinklers.

Wednesday, September 3, 2025

September 03, 2025

Corrective Action Plan (CAP)

Download the Corrective Action Plan (CAP) Form👈

Corrective Action Plan (CAP) is a structured document that helps an organisation to identify the actions required to correct an issue previously identified and ensure its recurrence is prevented by delegating and implementing the suggested actions. It is used in almost all kinds of industries. It outlines the necessary steps to correct an issue and prevent a similar situation in the near future.

A well-developed CAP consists of the following elements, usually;

  • Problem identification
  • Root Cause Analysis (RCA)
  • Action Plan
  • Responsibility Assigned To
  • Time Frame
  • Comments

Saturday, May 31, 2025

May 31, 2025

Method Statement for Lifting & Moving Material at Worksite Using Mobile Crane & Forklift

Download the Method Statement for Lifting and Moving Material at Worksite Using Mobile Crane and Forklift👈


The method statement is a draft outlining the activities involving the use of the mobile crane and forklift while moving material at the worksite. It encompasses information about the hazards, risks, and control measures required to adapt when handling material onsite.

The organization using this document must amend it according to the nature of the work activity, the equipment being used, and the loads being moved. It should be made robust after conducting the risk assessment of the work activity, considering all factors.

Sunday, May 11, 2025

May 11, 2025

Method Statement for General Lifting Operations

Download the General Lifting Method Statement

The general Lifting Method Statement provides the guidelines about the lifting operation, the associated hazards, and the method to lift the object while maintaining the safety and health throughout the work activity.

Most of the work activities involving lifting and lifting equipment fail  due to incompetent operatives, lack of risk assessment, poor planning, or wrong use of the lifting equipment and the accessories. Moreover, the load being lifted must be installed with the reasonable liftig points otherwise attachments used at the wrong point also lead to incidents e.g., collapse of equipment and the load.



Saturday, January 11, 2025

January 11, 2025

Scaffolding Inspection Checklist

Download the Scaffolding Inspection Checklist Form👈

Working at Height is an important but dangerous activity. A thorough and comprehensive risk assessment is necessary to identify the risks and determine what kind of work platform is suitable for the activity. Scaffolding is one of the available means of working at height.

Due to the work platform's nature and structure, the scaffolding's inspection regime must be performed by a competent yet experienced professional. The best method is to utilize a comprehensive inspection checklist covering all aspects of the working platform and inspecting every element. The observations and notes are recorded, and if the work platform is in good condition, it can be used; otherwise, label it dangerous and remove it from the site.