Job Safety Analysis (JSA) - Scaffolding Erection & Dismantling

Download the Scaffolding Erection & Dismantling - Job Safety Analysis (JSA)👈

Scaffolding is a working platform used to work at height. Scaffolding is available in various forms to perform work activities in various locations which include the following ones;

  1. Tower Scaffolding;
  2. Single Scaffolding
  3. Cantilever Scaffolding
  4. Suspended Scaffolding
The erection and dismantling of the scaffolding is also a hazardous activity due to various factors including the fall from height during erection, contact with overhead lines, imbalance during scaffolding erection and dismantling, etc.

Moreover, if the scaffolding is erected by an incompetent person the risk of collapse exists, and the structure collapse can lead to severe consequences. It is mandatory that each and every step is assessed by a competent person before the erection/dismantling job commencement and make sure it is done safely. All of the hazards and risks are accounted for and risk level is mitigated to minimum workers are provided with a Safe System of Work (SSoW), a Safe Workplace, Correct tools, Training is provided, and workers are provided with PPEs and Fall Protection to ensure the minor risk of fall is also countered.

All of this can be achieved if the Job Safety Analysis is performed. The job safety analysis is a Hazard Identification technique that divides the main activity into steps and even further to ensure each step of the activity is analyzed & assessed individually and relevant controls are adapted for implementation. In layman's terms, the risk associated with each step of the main activity is assessed separately and managed.

Follow the link available above and download the Job Safety Analysis of the Scaffolding Erection and Dismantling job as a sample, and modify it as per requirements.



Friday, December 9, 2022

December 09, 2022

Onsite & Public Road Traffic Management & Planning Procedure

Download the Onsite & Public Road Traffic Management & Planning Procedure👈

In the routine work activities on the worksite, the onsite traffic is a part of the work activity being used to shift the load and the equipment from location to location while the other transportation is also used to bring in new material, tools, and equipment.

It also poses a serious threat to the onsite workers who can be injured in case of an accident. Furthermore, the management can also lead to a reduction in terms of loss of property, time, and cost while the project can be completed on time and chain management can stay effective.

The organization must ensure that the onsite traffic is managed and workers are provided with a safe work site, and working environment. ILO Convention C155, Article 16 also requires the employer to take reasonably practicable and ensure workers are also safe.

Use the link available above and download the document.

Monday, December 5, 2022

December 05, 2022

Method Statement for General Plumbing

Download the Method Statement for General Plumbing👈

General Plumbing is part of the construction and routine repair maintenance. The piping joints are made and repaired to make sure there is no leakage. The correct tool and equipment help in effective work completion.

In addition to that, the work also requires the work is performed safely, the correct prevention measures are adopted and implemented and the risk level is mitigated to the minimum level so that the regulatory requirements are met. The employer must take reasonable measures to protect the workers and meet legal requirements. [Ref: Article 16 of Convention C155]

Furthermore, the workers should be trained to perform the job activity, well aware of their responsibilities and job description. The workers are also required to take reasonable care of themselves and others who might be harmed due to their negligence or work activities. [Ref: Article 19 of C155]

Moreover, there should be concrete cooperation between the management and the workers/ worker representative when pursuing their actions as per articles 16 & 19. [Ref: Article 20 of C155]

Follow the link available above and download the document in the editable format.

Saturday, December 3, 2022

December 03, 2022

Warehouse Inspection Checklist

Download the Warehouse Inspection Checklist👈

A warehouse is a place for the storage of goods and items in large quantities, just like an amazon warehouse which is used to store the items for a certain period of time and in massive quantities. The warehouse is used for various purposes e.g., chemical storage, clothes storage, articles, and other things which can be stored simultaneously or separately.

The risk of fire ignition still exists due to the nature of the material stored and ignition sources available, therefore the organization must ensure the warehouse is safe and inspected through a systematic inspection regularly.

The requirements are;

  1. The housekeeping is maintained;
  2. The layout of the building is as per regulatory requirements and provided with adequate escape routes;
  3. The workplace is provided with firefighting arrangements in a functional state;
  4. The workers are trained and competent enough to use the firefighting arrangements;
  5. The electrical appliances and gadgets are inspected and available in good condition;
  6. The warehouse surface is clean and provided with adequate lighting arrangements;
  7. The local exhaust ventilation and the fresh air supply mechanism are provided and functional;
  8. The fire detection and fire alarm are provided and functional;
  9. Observations are made and suggestions are given to correct the loopholes and mistakes available;
  10. The next inspection date is provided and recorded;
Follow the link available above and download the document in the editable form.